- Wednesday September 6th, utility adjustments on Brucewood Rd, Turner St., 100 block of S Carlisle St., and 800 block of W Iowa Ave.
- Thursday September 7th and Friday September 8th. Paving on Turner St., 100 block of S Carlisle St., and 800 block of W Iowa Ave.
- Monday September 11th, Milling Brucewood Rd. and Paving the Reservoir Park Rd & parking lot.
- Tuesday September 12th, Paving Brucewood Rd.
- Wednesday September 13th, Thursday September 14th., and Friday September 15th. Paving Brucewood Rd and Reservoir Park Rd. and will have the pavement lines restriped.
As with all projects this is dependent upon weather conditions to remain on this schedule.